This article is Part 5 of a five-part educational series developed to meet continuing education (CE) credit requirements. Start with Article 1
At this point, you have adopted the “whole-enclosure mindset,” taking a systems-approach to the bulk water control layer, the air control layer, the vapor control layer, and the thermal control layer. Recognizing that transitions from one assembly to another is often the weak link in the chain of barrier continuity, you have taken measures to meet the latest codes and standard for air tightness characteristics as well as below-grade waterproofing that will ensure greater resilience regarding both durability and indoor environmental quality – all designed and detailed pursuant to LEED v5 BD+C. Mission accomplished? Not hardly. All that has been accomplished to this point is simply creating the conditions for success. Ultimate achievement rests upon execution and verification – and failure often lurks in the gap between what the drawings assumed and what was built.
How can project teams mitigate this gap? The simple answer is verification with documented evidence. This is the essence of building enclosure commissioning (BECx) and under LEED v5, BECx shifts from a nice-to-have to a certain degree of must-have.
Whole-building air leakage BECx shifts from optional to mandatory in LEED v5.
BECx has existed as a discipline for two decades. And it has been cited as an optional path for enhanced commissioning in LEED for over a decade. Under LEED v4/4.1 BD+C, two points can be achieved through the Enhanced Commissioning credit by completing a list of noted commissioning process (CxP) activities for the building’s thermal envelope in accordance with the National Institute of Building Sciences (NIBS) Guideline 3-2012, Exterior Enclosure Technical Requirements for the Commissioning Process, ASHRAE Guideline 0–2005, The Commissioning Process, and formalized further by ASTM E2947 (now ASTM E2947-21a), Standard Guide for Building Enclosure Commissioning, as they relate to energy, water, indoor environmental quality, and durability. Through LEED v4 and v4.1, no BECx scope was mandatory; the envelope scope was just an option; easy to skip.
LEED v5 BD+C changed this as the EAp2 Minimum Energy Efficiency prerequisite requires compliance with ANSI/ASHRAE/IES Standard 90.1-2019: Energy Efficiency Standard for Buildings Except Low-Rise Residential Buildings, which includes the following item under the mandatory provisions of Section 5 (Building Envelope):
5.4.3.1.1 Whole-Building Air Leakage
Whole-building pressurization testing shall be conducted in accordance with ASTM E779 or ASTM E1827 by an independent third party. The measured air leakage rate of the building envelope shall not exceed 0.40 cfm/ft2 under a pressure differential of 0.3 in. of water, with this air leakage rate normalized by the sum of the above-grade and below-grade building envelope areas of the conditioned space and semi-heated space.
As such, EAp3 pulls in Standard 90.1-2019’s field verification by reference, making the whole-building air leakage test in Section 5.4.3.1.1 a LEED requirement, including third-party testing per ASTM E779 or E1827, at a maximum rate of 0.40 cfm/ft2 – which is a consistent escalation in airtightness requirements observable across ASHRAE and ICC model documents.
Moreover, the LEED v5 BD+C EAp3 Fundamental Commissioning prerequisite requires the commissioning provider (CxP) to be engaged by the end of Design Development and to complete at least one enclosure design review before construction begins – the last point in time in which an outside reviewer could still catch a base-of-wall transition gap or an unresolved hand-off between certain subcontractors.
The LEED v5 prerequisite requirements are deliberately narrow, though, on their own, they do establish fairly robust requirements to better ensure that a building enclosure will be airtight.
Enhanced commissioning fills the gap.
LEED v5 BD+C pulls in a much more wholistic scope of BECx under the EAc5 Enhanced Commissioning credit. Though only worth 1 point in the rating system, Path 2 requires compliance with all tasks and deliverables referenced with ASTM E2947-21a except Sections 7.2.4 (Schematic Design Independent Design Review) and 7.4.3 (Construction Documents Independent Design Review). This means, substantially, almost the entire scope of E2947-21a applies: from a mock-up test review to additional site visits and field testing beyond air leakage to incorporate water penetration testing and infrared (IR) imaging.
EAc5 explicitly notes three types of field testing and offers optional referenced documents pursuant to each.
Type of Field-Testing | Referenced Documents (at least one required for each type per LEED v5) |
Building air leakage testing (note: ASHRAE 90.1-2019 references ASTM E779 or ASTM E1827) | ASTM E783: Standard Test Method for Field Measurement of Air Leakage Through Installed Exterior Windows and Doors
|
| ASTM E779: Standard Test Method for Determining Air Leakage Rate by Fan Pressurization |
| ASTM E1186-22: Standard Practices for Air Leakage Site Detection in Building Envelopes and Air Barrier Systems
|
| ASTM E3158: Standard Test Method for Measuring the Air Leakage Rate of a Large or Multizone Building
|
Water penetration testing | ASTM E1105: Standard Test Method for Field Determination of Water Penetration of Installed Exterior Windows, Skylights, Doors, and Curtain Walls, by Uniform or Cyclic Static Air Pressure Difference
|
| AAMA 501.2: Quality Assurance and Diagnostic Water Leakage Field Check of Installed Storefronts, Curtain Walls and Sloped Glazing Systems
|
Infrared imaging | ASTM C1153: Standard Practice for Location of Wet Insulation in Roofing Systems Using Infrared Imaging
|
| ASTM C1060: Standard Practice for Thermographic Inspection of Insulation Installations in Envelope Cavities of Frame Buildings
|
In accordance with ASTM E2947-21a, BECx runs through predesign (e.g., developing the Owner’s Project Requirements and documented performance goals), design (e.g., CxP technical review of issues sets), construction (e.g., submittal reviews, site observations, field testing), and occupancy (e.g., field observation log, issues-and-resolutions log).
EAc5 also notes that during occupancy, the building enclosure commissioning provider (BECxP) must review the training materials to confirm that they meet the training requirements provided in the BECx plan or specification, and confirm that the training occurred.
LEED v5 and its referenced standards and guiding practice documents emphasize construction and occupancy-phase criteria for a very practical reason: the enclosure is field-assembled by many trades in whatever weather may occur, and as such the resulting performance can’t be fully verified until the building is completely enclosed.
It is not just about energy.
An air-tight enclosure, with successful bulk water management and continuity of the thermal barrier will drastically improve the energy performance of a building and lend to greater long-term durability. Additionally, there is a health, safety, and welfare concern. Envelope issues are a leading driver of construction defect litigation. Moisture that goes undetected because no one verified continuity can lead to mold and deterioration of building materials, potentially causing negative impacts on indoor air quality and eventually undermine the integrity of the assembly as it breaks down. As with all commissioning, BECx verifies, while corrective measures are still possible, that requirements in the contract documents are met.
The essential playbook should start with the following:
Designate BECx scope explicitly in Division 01, naming roof, wall, below-grade and fenestration assemblies.
Engage the BECxP by the end of the Design Development phase; requiring a documented enclosure design drawing review before Construction Documents are finalized.
Reference ASTM E2813/E2947-21a and ANSI/ASHRAE/IES Standard 202-2024 by name in the commissioning specification.
Require air leakage testing per ASTM E779 or E1827 at 0.40 cft/ft2, regardless of certification pursuits.
Make sure water penetration testing and infrared imaging are identified in the commissioning specification along with their appropriate referenced documents.
Sequence submittal reviews and field observations toward low-recourse conditions first (such as below-grade before backfill and transitions ahead of cladding).
Simply put: the whole-building mindset with BECx is a dynamic duo.
The basic position here is that the building enclosure performs best when designed as one system – but too often we consider it one assembly at a time. By implementing a whole-enclosure mindset throughout design and then specifying building enclosure commissioning, projects will be more energy efficient, healthier, more durable, and less expensive to maintain. It is the classic principle: invest more upfront to save exponentially more later. And if you want to hit the “easy button” toward this end: pursue LEED v5 certification and require BECx under Enhanced Commissioning.
Sources
ASHRAE, 2005. ASHRAE Guideline 0-2005, The Commissioning Process. Peachtree Corners, Georgia: ASHRAE.
ASHRAE, 2024. ANSI/ASHRAE/IES Standard 202-2024, The Commissioning Process Requirements for New Buildings and New Systems. Peachtree Corners, Georgia: ASHRAE.
ASHRAE, 2019. ANSI/ASHRAE/IES Standard 90.1, Energy Standard for Sites and Buildings Except Low-Rise Residential Buildings. Peachtree Corners, Georgia: ASHRAE.
ASTM International, 2019. ASTM E779-19, Standard Test Method for Determining Air Leakage Rate by Fan Pressurization. West Conshohocken, PA: ASTM International.
ASTM International, 2022. ASTM E1827-22, Standard Test Methods for Determining Airtightness of Buildings Using an Orifice Blower Door. West Conshohocken, PA: ASTM International.
ASTM International, 2022. ASTM E1186-22, Standard Practices for Air Leakage Site Detection in Building Envelopes and Air Barrier Systems. West Conshohocken, PA: ASTM International.
ASTM International, 2024. ASTM E3158-24, Standard Test Method for Measuring the Air Leakage Rate of a Large or Multizone Building. West Conshohocken, PA: ASTM International.
ASTM International, 2018. ASTM E783-02(2018), Standard Test Method for Field Measurement of Air Leakage Through Installed Exterior Windows and Doors. West Conshohocken, PA: ASTM International.
ASTM International, 2015. ASTM E1105-15, Standard Test Method for Field Determination of Water Penetration of Installed Exterior Windows, Skylights, Doors, and Curtain Walls, by Uniform or Cyclic Static Air Pressure Difference. West Conshohocken, PA: ASTM International.
ASTM International, 2018. ASTM E2813-18, Standard Practice for Building Enclosure Commissioning. West Conshohocken, PA: ASTM International.
ASTM International, 2021. ASTM E2947-21a, Standard Guide for Building Enclosure Commissioning. West Conshohocken, PA: ASTM International.
ASTM International, 2023. ASTM C1153-23, Standard Practice for Location of Wet Insulation in Roofing Systems Using Infrared Imaging. West Conshohocken, PA: ASTM International.
ASTM International, 2015. ASTM C1060-11a(2015), Standard Practice for Thermographic Inspection of Insulation Installations in Envelope Cavities of Frame Buildings. West Conshohocken, PA: ASTM International.
Fenestration and Glazing Industry Alliance, 2025. AAMA 501.2-25, Quality Assurance and Diagnostic Water Leakage Field Check of Installed Storefronts, Curtain Walls and Sloped Glazing Systems. Schaumburg, Illinois: FGIA.
National Institute of Building Sciences, 2012. NIBS Guideline 3-2012, Exterior Enclosure Technical Requirements for the Commissioning Process. Washington, DC: National Institute of Building Sciences.
USGBC, 2025. LEED v5 Building Design and Construction. Washington, DC: U.S. Green Building Council.